PR-MAINT (Maintenance Processor [TN2404/TN790
RISC Systems])
Issue 4 May 2002
10-1371
555-233-123
Table 10-507.
TEST #102 MTP Outpulse Relay Test
Error
Code
Test Result
Description/Recommendation
100
ABORT
The test did not complete within the allowable time period.
1. Retry the command.
1018
ABORT
The test has been disabled via administration.
1. To enable the test, issue the change
system-parameters maintenance command, and set
the test remote access port field to “y.” (If you have an
INADS line, set the field to “y.”
2. Rerun the test.
1030
ABORT
This test is not run on the Standby SPE.
1131
ABORT
INADS port is busy because the system is reporting alarms
to INADS, or because INADS is dialed into the system.
1. If INADS is communicating with the switch the INADS
trunk is working. There is no need to run this test.
2. Or if required. Wait about ten minutes (until the INADS
session is terminated) and then re-enter the command.
1000
ABORT
System software resources required for this test are not
available.
1. Retry at 1-minute intervals a maximum of 5 times.
1050
ABORT
System could not determine if the testing of the INADS port
is administered.
1. Enter the change system-parameters maintenance
command. Verify that the “Test Remote Access Port?”
field is set to “y.”
2. Retry the command at 1-minute intervals a maximum of
5 times.
2033,
2500
Internal system error
1. Retry at 1-minute intervals a maximum of 5 times.
2000
ABORT
MTP did not respond to the test request.
1. Repeat the test at 1-minute intervals a maximum of 5
times.
2. If all MTP tests are aborting, execute the test processor
a/b long command in order to reset MTP and to
examine the results of the MTP Reset Test (#101).
3. Replace the Processor circuit pack.
4. If only the MTP outpulse relay test is aborting, escalate
problem.
Continued on next page
Содержание Definity SI
Страница 1: ...0DLQWHQDQFH IRU YD D 1 7 6HUYHU 6 Volumes 1 2 and 3 555 233 123 Issue 4 May 2002...
Страница 62: ...Maintenance Architecture 555 233 123 1 26 Issue 4 May 2002...
Страница 92: ...Management Terminals 555 233 123 3 26 Issue 4 May 2002...
Страница 204: ...Routine Maintenance Procedures 555 233 123 5 100 Issue 4 May 2002...
Страница 250: ...LED Interpretation 555 233 123 7 10 Issue 4 May 2002...
Страница 2763: ...VC DSPPT Issue 4 May 2002 10 1977 555 233 123 Figure 10 107 VC Circuit Pack DSP Port Local TDM Loopback Test...
Страница 2776: ...Maintenance Object Repair Procedures 555 233 123 10 1990 Issue 4 May 2002 Figure 10 109 VC Circuit Pack Summer Port Loopback Test...
Страница 2804: ...Maintenance Object Repair Procedures 555 233 123 10 2018 Issue 4 May 2002...
Страница 2968: ...Index 555 233 123 IN 10 Issue 4 May 2002...