PE-BCHL (PRI Endpoint Port)
Issue 4 May 2002
10-1215
555-233-123
Conference Circuit Test (#7)
One or more Network Processing Elements (NPEs) reside on each circuit pack
with a TDM Bus interface. (The TN464C UDS1 circuit pack has one
SCOTCH-NPE chip instead of several NPE chips.) The NPE controls port
connectivity and gain, and it provides conferencing functions on a per port basis.
The Conference Circuit test verifies that the NPE channel for the port being tested
can correctly perform the conferencing function. The NPE is instructed to listen to
several different tones and to conference the tones together. The resulting signal
is then measured by a tone detector port. If the level of the tone is within a certain
range, the test passes.
1117
ABORT
A service state audit message is outstanding.
1. Wait 2 minutes and then try again.
2000
ABORT
Response to the test request was not received within the
allowable time period.
1. Retry the command at 1-minute intervals a maximum of 5
times.
2020
ABORT
The test did not run due either to an already existing error on
the specific port or to a more general circuit pack error.
1. Examine the Error Log for existing errors against this port
or the circuit pack and attempt to diagnose the already
existing error.
2100
ABORT
Could not allocate the necessary system resources to run this
test.
1. Retry the command at 1-minute intervals a maximum of 5
times.
Any
FAIL
The NPE of the tested port was found to be transmitting in
error. This causes noisy and unreliable connections. The
PE-BCHL is moved to the out-of-service/near-end state.
1. Replace the circuit pack.
PASS
The port is able to communicate over the TDM Bus.
Table 10-452.
TEST #6 NPE Crosstalk Test — Continued
Error
Code
Test
Result
Description/Recommendation
Continued on next page
Содержание Definity SI
Страница 1: ...0DLQWHQDQFH IRU YD D 1 7 6HUYHU 6 Volumes 1 2 and 3 555 233 123 Issue 4 May 2002...
Страница 62: ...Maintenance Architecture 555 233 123 1 26 Issue 4 May 2002...
Страница 92: ...Management Terminals 555 233 123 3 26 Issue 4 May 2002...
Страница 204: ...Routine Maintenance Procedures 555 233 123 5 100 Issue 4 May 2002...
Страница 250: ...LED Interpretation 555 233 123 7 10 Issue 4 May 2002...
Страница 2763: ...VC DSPPT Issue 4 May 2002 10 1977 555 233 123 Figure 10 107 VC Circuit Pack DSP Port Local TDM Loopback Test...
Страница 2776: ...Maintenance Object Repair Procedures 555 233 123 10 1990 Issue 4 May 2002 Figure 10 109 VC Circuit Pack Summer Port Loopback Test...
Страница 2804: ...Maintenance Object Repair Procedures 555 233 123 10 2018 Issue 4 May 2002...
Страница 2968: ...Index 555 233 123 IN 10 Issue 4 May 2002...