Maintenance Object Repair Procedures
555-233-123
10-1364
Issue 4 May 2002
PPP Link Status Inquiry Test (#1279)
This non-destructive test determines the state of the PPP link. The test passes
only if the link is up.
Table 10-504.
TEST #1279 PPP Link Status Inquiry Test
Error
Code
Test
Result
Description/Recommendation
1124
ABORT
ppp link is not enabled.
1. Verify that the ppp link is enabled (status port UUCSSpp,
status link n, or display data-module).
2. If the link is not enabled, enable the link (change
data-module).
3. Repeat the test.
4. Escalate if the problem persists.
1125
ABORT
PPP Link is not in service.
1. Verify whether PPP link is in-service (status port
UUCSSpp or status link n).
2. If the PPP link is not in service, release the link (release
link n or release port UUCSSpp).
3. Repeat the test.
4. Escalate if the problem persists.
2100
ABORT
Could not locate the necessary system resources to run this
test.
1. Retry the command at 1-minute intervals, up to 5 times.
2. Escalate if the problem persists.
2500
ABORT
Internal system error.
1. Retry the command at 1-minute intervals, up to 3 times.
2. Escalate if the problem persists.
Continued on next page
Summary of Contents for Definity SI
Page 1: ...0DLQWHQDQFH IRU YD D 1 7 6HUYHU 6 Volumes 1 2 and 3 555 233 123 Issue 4 May 2002...
Page 62: ...Maintenance Architecture 555 233 123 1 26 Issue 4 May 2002...
Page 92: ...Management Terminals 555 233 123 3 26 Issue 4 May 2002...
Page 204: ...Routine Maintenance Procedures 555 233 123 5 100 Issue 4 May 2002...
Page 250: ...LED Interpretation 555 233 123 7 10 Issue 4 May 2002...
Page 2804: ...Maintenance Object Repair Procedures 555 233 123 10 2018 Issue 4 May 2002...