m. Error Type 1303 — DS1 circuit pack suffix incorrect for CSU Module/T1
Sync Splitter or for E1 Synchronization Splitter.
DS1 circuit pack suffix incorrect for CSU Module/T1 Sync Splitter: The
Near-End CSU Type
field on the add ds1 form has been administered
as
integrated
but the DS1 circuit pack is not a TN464F or later suffix
UDS1 board.
If the 120A1 CSU Module or the 401A T1 Sync Splitter is to be used,
remove the circuit pack and replace it with a TN464F or later suffix board.
Otherwise, use the change ds1 command to change the
Near-End CSU
Type
field to
other
.
DS1 circuit pack suffix incorrect for E1 Synchronization Splitter: The
E1 Sync-Splitter?
field on the add ds1 form has been administered
as
y
but the DS1 circuit pack is not a TN464F or later suffix UDS1 board.
If the 402A or 403A E1 Synchronization Splitter is to be used, remove the
circuit pack and replace it with a TN464F or later suffix board. Otherwise,
use the change ds1 command to change the
E1 Sync-Splitter?
field
to
n
.
n. Error Type 1310 — BLB failure. This error occurs when the DS1 Board
Loopback (BLB) demand test fails. Repeat the test using the commands
busyout board UUCSS, test ds1-loop UUCSS ds1/csu-loopback-tests,
release board UUCSS. If the BLB test continues to fail, then the TN464F
circuit pack needs to be replaced.
o. Error Type 1311 — ELB failure. This error occurs when the Equipment
Loopback (ELB) test fails for the Integrated CSU (I-CSU) Module/T1 Sync
Splitter or for the 402A or 403A E1 Synchronization Splitter. This test is
executed by the I-CSU/E1SS during I-CSU/E1SS power-up/reset (i.e.-
UDS1 board physically inserted and 120A1 CSU Module or the 401A T1
Sync Splitter, or the 402A or 403A E1SS is already installed) or when the
120A1 CSU Module or the 401A T1 Sync Splitter, or the 402A or 403A
E1SS is plugged on to an already initialized UDS1 DS1 board.
NOTE:
For the I-CSU/T1 Sync Splitter only, the ELB test is also executed
as part of the command test ds1-loop UUCSS
ds1/csu-loopback-tests. Attempt to clear the alarm using the
commands busyout board UUCSS, test ds1-loop UUCSS
ds1/csu-loopback-tests, release board UUCSS. If the ELB test
continues to fail, then either the UDS1 board, the CSU Module, or the
I/O cable between the backplane and the CSU module (or any
combination thereof) has failed. Attempt to isolate where the failure is
occurring by re-executing the test and by replacing one piece of
hardware at a time.
Содержание DEFINITY Server CSI
Страница 1: ...Maintenance for Avaya DEFINITY Server CSI Volumes 1 and 2 Release 1 2 555 233 119 Issue 5 October 2002...
Страница 6: ......
Страница 20: ...Contents 555 233 119 20 Issue 5 October 2002...
Страница 30: ...About this Book 555 233 119 30 Issue 5 October 2002...
Страница 944: ...Maintenance Objects 555 233 119 944 Issue 5 October 2002...
Страница 1397: ...MMI BD Issue 5 October 2002 1397 555 233 119 Figure 44 TN787 Multimedia Interface MMI Circuit Pack...
Страница 1409: ...MMI PT Issue 5 October 2002 1409 555 233 119 Figure 45 TN787 Multimedia Interface MMI Circuit Pack...
Страница 1891: ...VC DSPPT Issue 5 October 2002 1891 555 233 119 Figure 63 VC Circuit Pack DSP Port Local TDM Loopback Test...
Страница 1902: ...Maintenance Objects 1902 Issue 5 October 2002 Figure 65 VC Circuit Pack Summer Port Loopback Test...