Install Telecommunications Cabling
Task List: Installing the Telecommunications Cabling
SI Installation and Upgrades
403
June 2004
Install Telecommunications Cabling
This section provides both information about installing the telecommunications cabling and procedures
for doing the installation.
Information about Installing the Cabling
•
Provisioning Plan
on page 404
•
Main Distribution Frame (MDF) Hardware
on page 404
•
MDF Cross-Connect Fields
on page 406
•
Main Distribution Frame
on page 408
•
Main Distribution Frame Labels
on page 409
•
Off-Premises Circuit Protection
on page 410
•
Cable Installation
on page 411
•
Sneak Fuse Panels
on page 411
•
Coupled Bonding Conductor
on page 415
•
Installation Space Requirements
on page 416 for the sneak fuse panels, the 110-type hardware,
and the Cable Slack Manager
•
Station Wiring Design
on page 417
•
Station Circuit Distribution from Equipment Room
on page 421
•
Layout
on page 427
•
Patch Cord/Jumper Installation and Administration
on page 429
Task List: Installing the Telecommunications Cabling
1
Label Control Carrier Cable
on page 431
2
Connect Control Carrier Outputs Cable
on page 432
3
Connect Trunk Pairs Using Concentrator Cables
on page 432
4
Connect Trunk Pairs to Cabinet Using Jumper Wires To Establish 3-Pair Modularity
on page 433
5
Install Cables Between Cabinet and MDF
on page 435
6
Install Connector Cables Between Auxiliary Cabinet and MDF
on page 436
7
Mount 110A- or 110P-type terminal blocks on the wall
on page 437 or
Mount 110P-type terminal
blocks on a frame
on page 439
8
Install Cable Slack Managers
on page 441
9
Install Sneak Fuse Panels
on page 443
10
Install Coupled Bonding Conductor
on page 445
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...