Installing the Stratum 3 Clock
Task List: Install the Stratum 3 clock
694
SI Installation and Upgrades
June 2004
Return to Task List
Connect AC Power to Stratum 3 Clock Cabinet
Return to Task List
The clock cabinet requires a 120 VAC, 15 amp receptacle. The green wire ground provided by the
receptacle is sufficient. The clock cabinet does not require a ground connection back to the single-point
ground.
Check and Connect Commercial AC Power
Return to Task List
1
Before powering up the system, check the AC power using a KS-20599 digital voltmeter (DVM)
(or equivalent).
2
Set the DVM to the 250 volt range.
3
Carefully measure the voltage between the hot and neutral side of the receptacle. The neutral wire
is white, the hot wire is black.
4
Verify the meter reads 106 to 128 VAC. If not, have a qualified electrician correct the problem.
5
Measure the voltage between the neutral and ground side of the receptacle. The ground wire is
green.
6
Verify the meter reads 0 VAC. If not, have a qualified electrician correct the problem.
7
Set all cabinet power modules OFF. Plug the AC power cable into the receptacle.
Return to Task List
Connect DC Power and Ground to Stratum 3
Clock Cabinet
Return to Task List
Provide power for the clock cabinet from the same DC power plant as the DEFINITY ECS.
Ground the clock cabinet to the DC power plant.
Connect Clock Cabinet Grounding
Return to Task List
1
Measure and cut a 6 AWG (#40) (16 mm
2
) wire long enough to reach from the clock cabinet to
the ground discharge bar in the DC power plant.
2
Insert 1 end of the wire into the ground lug on the clock cabinet and tighten the screw.
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...