System 75 XE to R8si (Blowback)
Task List: System 75 XE to R8si
SI Installation and Upgrades
251
June 2004
Connect TDM/LAN cables and ICC cables for PPN Upgrade [75 XE upgrade]
Return to Task List
NOTE:
This procedure is for single cabinet (PPN) upgrades only.
Use this procedure to route and connect the new WP-91716 L3 TDM/LAN cables between the System 75
XE port cabinets that are being reused.
CAUTION:
Do not run the new cables through the existing slot in the rear shelves.
1
Working from the rear of the cabinets, loosen the 2 screws on the left side of the connector-panel,
and then remove the other 2 connector-panel screws.
2
Attach the TDM/LAN cable to the backplane, and slide the cable between the connector panel and
the rear shelf.
Do not run the cable through the existing slot in the rear shelves.
3
Route the cable along the bottom of the cabinet.
4
Replace and tighten the connector-panel screws.
5
For a duplicated system, connect the ICC cables as shown in this table:
For the locations of the pin-field blocks, see
Figure 53, ICC pin-field blocks on J58890L-1 L5
enhanced control cabinet,
on page 252 or
Figure 54, ICC pin-field blocks on J58890M-1 L5 or
J58890M-2 L7 enhanced duplicated control cabinet,
on page 253.
6
On the A carrier, verify that the 982LS current limiter (CURL) is properly connected to the pin-
field block marked CURL (see
Figure 53, ICC pin-field blocks on J58890L-1 L5 enhanced
control cabinet,
on page 252). The CURL’s components should be on the left side as viewed from
the rear.
Table 10: Intercabinet cable connections — PPN
FROM: Carrier
Pin-Field Block
TO: Carrier
Pin-Field Block
J58890L-1 L5
ICCB
J58890M-1 L5
ICCB
ICCC
ICCC
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...