G3iV4 to Avaya Communication Manager
Task List: G3iV4 to Avaya Communication Manager
82
SI Installation and Upgrades
June 2004
Power up [from G3V4]
Return to Task List
Set the circuit breaker to ON.
CAUTION:
It may be necessary to reseat circuit packs. To prevent damage from static electricity,
always wear an Electromagnetic Compatibility (EMC) wrist strap (Comcode 900698226)
when handling all system components.
NOTE:
To prevent unnecessary trouble tickets, do not enable the system alarms (Alarm
Origination feature) until all installation and administration procedures are completed.
1
Power up the AC- or DC-powered system.
The results of system tests display on the monitor.
2
Verify that all tests pass.
If any of the terminal messages indicate a test has failed or if the message
spe down mode
is
displayed, refer to Maintenance for Avaya DEFINITY® Server SI (555-233-123) to clear the
trouble.
Return to Task List
For Single Carrier Cabinets (SCC1)
System
Steps
AC
a
Set the switch on the AC power panel to ON position (up).
b
Set the cabinet circuit breakers to ON.
This starts the system initialization and test. All red LEDs
on the circuit packs go on and then off.
DC
a
At the DC Battery Cabinet (if installed), set the circuit
breaker to ON.
b
At the DC Power Cabinet, set the circuit breaker(s) on the
rectifiers to ON.
This starts the system initialization and test. Some red
LEDs may be turned on, but they are turned off during the
boot-up process. No action is required.
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...