Test Telephones and Other Equipment
Perform Complete System Test
SI Installation and Upgrades
739
June 2004
Verify Timing to the System
Return to Task List
1
To administer the Stratum 3 clock, type
change synchronization
and press Enter.
2
Type 3 in the
stratum
field.
3
Type the port network number where the TN780 Tone-Clock circuit packs reside in the
port
network
field.
NOTE:
Wait 1 minute for the software to reconfigure the system synchronization.
4
Verify the results of test 649. If test 649 fails with a code of 2101, then check the wiring for
EXTSYN0 and EXTSYN1. Refer to Maintenance for Avaya DEFINITY® Server SI (555-233-
123).
If test 649 is successful, then the system is getting correct timing from the Stratum 3 clock.
Return to Task List
Perform Complete System Test
Return to Task List
Run the complete system test with the
Allports
option in the
SPE Interchange
and
Long
test modes. The
hardware group tests are described in the Maintenance for Avaya DEFINITY® Server SI (555-233-123)
documentation for your system.
NOTE:
This test takes several hours. It may be best to run the test in the background, or at night,
or both.
Resolve Alarms
Return to Task List
After the test has completed, inspect the alarms log. Type display alarms and resolve the alarms in the
usual manner.
Check the error log for evidence of failure. The only failure results logged should be the outcome of tests
requiring a connected station, where a station is not connected to the port under test. Repair all other
failures or refer them to a maintenance technician for repair.
Resolve any alarms that may exist using the Maintenance for Avaya DEFINITY® Server SI (555-233-
123) documentation for your system.
Return to Task List
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...