System 75 Small-Cabinet to R8si (Blowback)
Task List: System 75 Small Cabinet to R8si
SI Installation and Upgrades
285
June 2004
Task List: System 75 Small Cabinet to R8si
Ensure that these tasks are complete before the upgrade visit:
1
Verify the required hardware for a control-carrier replacement [75 small upgrade]
or
Verify the required hardware for a control cabinet replacement [75 small upgrade]
2
Provide the required tools [75 small upgrade]
Perform these tasks during the upgrade visit:
3
Inspect the new control carrier and install CURL [75 small upgrade]
or
Unpack the control
cabinet and inspect for damage [75 small upgrade]
4
Verify software load [75 small upgrade]
5
Verify system status [75 small upgrade]
Record any customer-placed busy-outs.
6
Save translations [75 small upgrade]
7
Verify external alarm connections; modify cabling if necessary [75 small upgrade]
8
Label cables [75 small upgrade]
For systems so equipped:
9
Shut down DEFINITY AUDIX system [75 small upgrade]
10
Power down [75 small upgrade]
11
Disconnect power and grounding [75 small upgrade]
12
Verify power failure [75 small upgrade]
if the system uses power failure stations
13
Open/remove doors and panels [75 small upgrade]
14
Disconnect TDM cables [75 small upgrade]
15
Remove circuit packs (A carrier only) [75 small upgrade]
or
Remove circuit packs (A and B
carriers) [75 small upgrade]
16
Remove tape drive [75 small upgrade]
17
Remove control carrier A [75 small upgrade]
18
Prepare and install new control carrier [75 small upgrade]
19
Install new control cabinet [75 small upgrade]
or
Install new control cabinet with earthquake
protection [75 small upgrade]
20
Install circuit packs [75 small upgrade]
21
Move 25-pair cables from System 75 to R8si [75 small upgrade]
22
Install TDM/LAN bus terminators and connect cables [75 small upgrade]
(The multi-carrier
cabinet requires the new ZAHF4 TDM bus terminators. Do not skip this!)
23
Verify TDM cables and connectors [75 small upgrade]
. If new TDM terminators and cables are
required but have not yet been installed, install them now.
24
Connect power and grounding [75 small upgrade]
25
Close upgraded PPN stack without earthquake protection [75 small upgrade]
or
Close upgraded
PPN stack with earthquake protection [75 small upgrade]
26
Install cable clamps [75 small upgrade]
27
Power up and set date, time and daylight savings rule [75 small upgrade]
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...