Test the System
Task List: Test the System
SI Installation and Upgrades
483
June 2004
Test the System
This section provides tests to:
•
review the status of the system
•
test the tone-clock, TDM bus, and duplication link in the Processor Port Network (PPN)
•
test the expansion interfaces, tone-clock(s), TDM buses, and duplication in the Expansion Port
Networks (EPNs).
These tests verify the Time Division Multiplexing (TDM) cables, terminators, and the Inter-Cabinet
Cables (ICC). If a FAIL Result code is seen or other problems are indicated, check these cables. If
problems persist, refer to the Maintenance for Avaya DEFINITY® Server SI (555-233-123)
documentation.
See
LED Indicators
on page 484 for information regarding the LED status indicators for the different
circuit packs.
NOTE:
Circuit pack positions are usually given by cabinet, carrier, and slot. They may also be
given by port. The term “cabinet” refers either to a stack of SCC1 (Single-Carrier
Cabinets) or to an MCC1 (Multi-Carrier Cabinet) making up one port network. A port
network is defined as a group of cabinets connected together with one TDM bus.
Task List: Test the System
CAUTION:
To prevent unnecessary trouble tickets, do not enable the system alarms (Alarm
Origination feature) until all installation and administration procedures are completed.
1
Check System Status for Each Cabinet
on page 487
2
Check Circuit Pack Configuration
on page 489
3
Test Time Division Multiplexing Bus in Processor Port Network
on page 490
4
Test Tone-Clock Boards
on page 491
5
Test SPE Duplication Memory Shadowing Link (if duplicated)
on page 492
6
Test Duplicated Switch Processing Element Interchange (if duplicated)
on page 492
7
Test Time Division Multiplexing Bus for Each Expansion Port Network
on page 494
8
Test Tone-Clock for Each Expansion Port Network
on page 495
9
Test Tone-Clock Interchange for Each Expansion Port Network
on page 495
10
Test Expansion Interface Exchange for Each Expansion Port Network
on page 495
11
Check Circuit Pack Configuration
on page 497
12
Save Translations, if Required
on page 497
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...