System 75 XE to R8si (Blowback)
Task List: System 75 XE to R8si
278
SI Installation and Upgrades
June 2004
8
Test Remote Access Interface
9
Test Basic Rate Interface
10
Test Duplication Option Processing
11
Element Interchange
12
Test Terminating Trunk Transmission
13
Test Stratum 3 Clock
14
Perform Complete System Test
15
Activate and Test Alarm Origination Feature
Return to Task List
Retranslate port circuits [75 XE upgrade]
Return to Task List
1
If port circuit packs in the R1V3 control cabinet were relocated, verify that they were retranslated
during the off-site software upgrade.
2
If they were not retranslated, you must retranslate them now.
Refer to DEFINITY® ECS R8.1 Administrator’s Guide (555-233-503) for instructions on
performing the retranslations.
Return to Task List
Readminister translation [75 XE upgrade]
Return to Task List
If the customer has added one or more components (for example, a call pickup group) to the system since
translation was done, the customer is responsible for readministering the translation.
Rerecord announcements [75 XE upgrade]
Return to Task List
If you have not saved and restored announcements during the upgrade, the customer must re-record all
announcements now.
If the customer changed any announcements after the they provided the source tape for the blowback
flash card, the customer must re-record the new announcements.
Return to Task List
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...