System 75 Small-Cabinet to R8si (Blowback)
282
SI Installation and Upgrades
June 2004
.
Upgrade preparation steps
What
When
Who
1
Check that circuit packs vintages are inspected.
Before upgr
Project Mgr
2
Check that all adjunct versions are compatible with the new
switch version.
Before upgr
Project Mgr
3
Verify expansion interface compatibility for packet bus
applications:
If the new system will have one or more expansion port
network cabinets and will run any packet applications, do not
reuse the TN776 expansion interface circuit packs; they must
be replaced with TN570 circuit packs.
Before upgr
Project Mgr
4
Identify proper TDM/LAN bus cables and terminators for the
system.
If PACCON is not currently enabled, the cables and
terminators may need to be replaced for V3 and later si
systems, R5/R6vs systems, and SRPs upgrading to Avaya™
Communication Manager.
Packet applications currently running in one port network do
not guarantee that the system has the correct hardware.
Adding a packet application to another network without
verifying the TDM/LAN bus cables and terminators
frequently causes upgrade problems.
We recommend that you schedule a time to replace the cables
and terminators before the upgrade. Note that this requires a
service outage.
Before upgr
Project Mgr
5
Check for software upgrade compatibility:
— current software patches that will need to be re-
applied
— software upgrades that include all relevant bug fixes
Before upgr
Project Mgr
6
Use the latest software QPPCN to check the vintages of all
circuit packs that will be reused in the upgrade.
a
Replace circuit packs that have unusable vintages.
b
Make a final vintage check.
For current information about usable vintages in a
DEFINITY ECS system, see the Stockable, Minimum
Usable Vintages, & Certifiable Vintages, COMPAS
ID 42751.
Before upgr
Design Spec
7
For blowback upgrades only:
Make the Blowback Tape
. The
blowback tape is converted and written to removable media.
This takes 2 weeks and must be done before the upgrade.
Before upgr
Tech or
Design Spec
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...