Test the System
LED Indicators
SI Installation and Upgrades
493
June 2004
Figure 187: Example System Status Report for All Cabinets
Return to Task List
Test Expansion Interface Circuit Packs
Return to Task List
Check each Expansion Interface (EI) circuit pack in the system.
1
Type
test board
UUCSS
where
UUCSS
is the cabinet, carrier, and slot for an Expansion Interface
(EI) circuit pack in the system, and press Enter.
NOTE:
Labels on the port network and carrier and on the strip under the circuit pack contain this
information.
2
Verify the screen displays test results similar to
Figure 188, Sample Test Results for Expansion
Interface Board 2A01,
on page 494. This example is for board 2a01.
3
If any result is
FAIL
, check the connections for the fiber optic link.
4
Repeat Steps 1 and 2 for each Expansion Interface circuit pack.
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...