Make the Blowback Tape
To upload the translations remotely, contact the CSA. If you choose to make a blowback tape, follow this
procedure:
NOTE:
There must always be 2 system tapes on site with the DEFINITY system. Do not send the
system or backup tape to the CSA.
1
Get a blank R1V3 tape from the regional CSA. This will be the blowback tape.
2
Remove the backup tape, install the blowback tape, and wait for the tape to retension.
NOTE:
The off-site CSA translation upgrade does not preserve the contents of recorded
announcements on TN750/B or earlier circuit packs. Therefore, if a TN750/B or earlier
circuit pack resides in the stack of single-carrier cabinets which is dismantled during the
upgrade, any announcements stored on the circuit pack must be rerecorded.
3
Enter
save translation
. Press Return.
4
Remove the blowback tape and label it with IL information (customer name and customer
contact).
5
Reinstall the system tape.
6
Use next-day delivery to mail the blowback tape to the CSA for use in making the translation
memory cards for the upgrade.
Task List: G3iV4 to Avaya Communication Manager
Use this task list when you are upgrading a DEFINITY G3iV4 PPN to Avaya Communication Manager.
Ensure that these tasks are complete before the upgrade visit:
1
Verify the required hardware [G3V4 to from R5/R6/R7/R8si]
2
Provide the required tools [from G3V4]
3
Go to the RFA website [from G3V4]
4
Pre-upgrade administration [from G3V4]
Perform these tasks during the upgrade visit:
5
Check existing software load [from G3V4]
to identify any software patches.
6
Disable scheduled maintenance and alarm origination [from G3V4]
7
Verify system status [from G3V4]
Record any customer-placed busy-outs.
8
Record all links and remove only ISDN interface links [from G3V4]
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...