Install and Connect MCC1 (Multicarrier) Cabinet
Task List: Install and Connect MCC1
330
SI Installation and Upgrades
June 2004
Each EPN cabinet is normally positioned adjacent to the PPN cabinet but may be located remotely in a
different room or a different building. A configuration can have up to 5 EPNs in a MCC1.
1
The procedure for installing an EPN cabinet is the same as for the PPN cabinet.
2
If earthquake protection is required,
Install Earthquake Protection for MCC1
.
3
If earthquake protection is not required, level the cabinets and adjust and lock the cabinet
stabilizing bolts to keep the cabinets from moving.
NOTE:
To install a new EPN cabinet to an existing system, refer to the Upgrades and Additions
for Avaya™ DEFINITY® Server R (555-233-115).
Return to Task List
Position the Auxiliary Cabinet (Optional)
Return to Task List
1
Position the Auxiliary cabinet next to the PPN cabinet (or EPN cabinet, if installed). The location
of equipment inside the Auxiliary cabinet is specified in the Customer Service Document (CSD).
2
If earthquake protection is required,
Install Earthquake Protection for MCC1
.
3
If earthquake protection is not required, level the cabinets and adjust and lock the cabinet
stabilizing bolts to keep the cabinet from moving.
Return to Task List
Install Auxiliary Cabinet Equipment
Return to Task List
The Auxiliary cabinet allows for carrier, 23-in. (58.4 cm) rack, or panel mounting of hardware. The
following equipment is furnished with the cabinet:
•
Fuse panel
—
Distributes -48 VDC power to fused cabinet circuits
•
Power receptacle strip
—
Provides switched and unswitched 120 VAC receptacles
•
DC connector block
—
Required when Auxiliary cabinet is powered by an external DC source
•
AC to DC power supply
—
Converts AC power provided by the AC power strip switched outlet
to the required DC voltage
Install equipment inside the cabinet as specified in the CSD. The following optional equipment can be
installed:
•
Audichron H9040 Wake-Up Announcement System
•
909A/B Universal Coupler
•
7400 Series Data Modules
•
Z77A Multiple Data Mounting
•
Fan Assembly
—
Requires 120 volt AC power
•
COMSPHERE 3000-series modems
•
External Channel Service Unit (CSU)
—
1 is required for each T1 carrier link
•
PagePac Paging System
—
3 models are available. All PagePac models require 120 VAC power.
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...