Install and Administer Trunks
Add DS1 Tie and OPS Trunks
SI Installation and Upgrades
671
June 2004
The TN722B DS1 Tie Trunk, TN767C (or later) DS1 Interface, and TN464GP or later DS1 Interface
circuit packs provide connections to a 1.544 Mbps or 2.08 Mbps DS1 facility as 24 independent 64-kbps
trunks.
Adding DS1 tie-trunk service may require a service interruption; notify the customer in advance as to
when the addition will be carried out.
Task List: Adding DS1 Tie and OPS Trunks
1
Upgrading from a TN722 to a TN767C
on page 671
2
Disable Scheduled Maintenance and Alarm Origination to INADS (DS1 Tie and OPS Trunks)
on
page 672
3
Save Translations (DS1 Tie and OPS Trunks)
on page 672
4
Shut Down DEFINITY LAN Gateway System (DS1 Tie and OPS Trunks)
on page 672
5
Shut Down DEFINITY AUDIX System (DS1 Tie and OPS Trunks)
on page 673
6
Power Down System (DS1 Tie and OPS Trunks)
on page 673
7
Add Circuit Packs (DS1 Tie and OPS Trunks)
on page 674
8
Power Up System (DS1 Tie and OPS Trunks)
on page 674
9
Enter Added Translations (DS1 Tie and OPS Trunks)
on page 674
10
Save Translations (DS1 Tie and OPS Trunks)
on page 674
11
Resolve Alarms (DS1 Tie and OPS Trunks)
on page 675
12
Deliver or Install License file (DS1 Tie and OPS Trunks)
on page 675
13
Adding TTC Japanese 2-Mbit Trunks
on page 677
Return to Task List
Upgrading from a TN722 to a TN767C
Return to Task List
1
Remove all TN722 trunk members from affected trunk groups.
2
Type
remove ds1
UUCSS
(the slot containing the TN722).
3
Remove the TN722 circuit pack.
4
Put the TN767C circuit pack into the same slot.
5
Wait until the red LED goes off. The hardware tests take 12 to 20 seconds to run. When the red
LED goes off, the tests have completed.
6
If the red LED stays on, reseat the board and repeat this step.
7
Type
add ds1
PCSS
.
8
Continue with appropriate procedures to set up members of trunk groups.
Return to Task List
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...