System 75 XE to R8si (Blowback)
Task List: System 75 XE to R8si
SI Installation and Upgrades
245
June 2004
Install port cabinets [75 XE upgrade]
Return to Task List
!
DANGER
:
The cabinet may weigh as much as 130 pounds and requires 2 handlers. Use caution
to avoid injury.
!
WARNING:
Before inserting or removing a circuit pack from a cabinet, put on a wrist strap and attach
its plug or clip to the cabinet’s frame.
1
Place the port cabinets into the positions from which they were previously removed (see
Figure
49, 4-cabinet R8si PPN — front view doors removed,
on page 246).
2
Replace the circuit packs and power supplies in port cabinets C and D if they were previously
removed.
3
Install the new labels on the front and rear of the port cabinets.
Содержание MCC1
Страница 38: ...Upgrades to Avaya Commnication Manager Made Easy Before you start 38 SI Installation and Upgrades June 2004 ...
Страница 326: ...Installation for MCC1 Multicarrier Cabinets Made Easy 326 SI Installation and Upgrades June 2004 ...
Страница 362: ... Single Carrier Cabinets Made Easy 362 SI Installation and Upgrades June 2004 ...
Страница 498: ...Test the System LED Indicators 498 SI Installation and Upgrades June 2004 ...
Страница 650: ...Add IP Solutions Task list Upgrade a TN802 to a TN802B 650 SI Installation and Upgrades June 2004 ...
Страница 692: ...Install and Administer Trunks Add TN1654 DS1 Converter r only 692 SI Installation and Upgrades June 2004 ...
Страница 770: ...Connecting and Handling Fiber Optic Cables Cleaning Fiber Optic Cables 770 SI Installation and Upgrades June 2004 ...
Страница 784: ...Connector and Cable Diagrams Pinout Charts DS1 Interface Cable H600 307 784 SI Installation and Upgrades June 2004 ...
Страница 792: ...UPS Installation for SCC1 EPN A Carrier Cabinet Task List Install UPS 792 SI Installation and Upgrades June 2004 ...
Страница 874: ...Index Z 874 SI Installation and Upgrades June 2004 ...