²
Start the synchronization stage, for example, externally with binary input signal or via the integrated
controller. You can use a synchroscope to trigger the start at synchronism, that is, at 12 hours. The dura-
tion until the close command then corresponds to a cycle with the duration 1/Δf. At a frequency differ-
ence of 0.1 Hz, the duration is thus 10 s.
²
Insofar as permissible, perform this attempt several time for oversynchronous switching and subsynchro-
nous switching.
²
The switching performance can be checked with an external recorder or the integrated fault recording
function. You have to start the fault recording explicitly.
²
You can repeat the blind switching attempts at the limits of the permissible voltage difference.
b) Attempt with synchronous systems:
²
Start the synchronization stage, for example, externally with binary input signal or via the integrated
controller.
²
Check the proper release for activation with the message log or via a fault record. You have to start the
fault recording explicitly. All activation conditions have to be fulfilled within the time
Delay close
command
.
If you observe the change between synchronous and asynchronous operation, raise the changeover
threshold
f-threshold ASYN<->SYN
slightly.
c) Attempt with synchrocheck:
²
If you use this function in conjunction with the manual synchronization, check the proper release for
closure.
²
Synchronize the generator manually. Start the synchronization stage externally via a binary input. Check
the proper release for closure with the indicatiion log or via the fault record. You have to start the fault
recording explicitly.
Functional Tests
10.2 Primary and Secondary Testing of the Synchronization Function
1062
SIPROTEC 5, High-Voltage Bay Controller, Manual
C53000-G5040-C015-9, Edition 11.2017
Summary of Contents for 6MD85
Page 8: ...8 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 30: ...30 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 46: ...46 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 172: ...172 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 514: ...514 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1056: ...1056 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1092: ...1092 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1204: ...1204 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1238: ...1238 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1252: ...1252 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...
Page 1256: ...1256 SIPROTEC 5 High Voltage Bay Controller Manual C53000 G5040 C015 9 Edition 11 2017 ...