CONTEXT
This scenario is to be used in planning and performing planned maintenance visits (
PM visits
).
•
Actions required in preparation for each PM visit are described in
•
Actions to be carried out on-site during each PM visit are listed in the tables in sections
.
The tables list each of the recommended on-site planned maintenance tasks. For each task, they
give the recommended frequency (
Int
.; interval between tasks in months) and the expected duration
(
Drn.
; time in minutes)
•
PM visits must be made at six-monthly intervals. The tables show a suggested sequence of tasks to
be performed at successive PM visits, in columns numbered from1 through 6. For each visit an "X" in
the column indicates that the corresponding task should be performed.
•
The total time required for each PM visit depends upon the tasks scheduled and any additional work,
such as FRU replacements, calibrations, etc., found to be required. The schedules proposed take
account of the estimated time for each task, so as to balance the times required for each visit.
•
The sums of estimated times for tasks specified at each visit are shown here:
•
If the customer has recently performed IQ-related tasks, you do not need to re-perform these tasks
during the PM visit.
•
Some local regulations may require you to peform additional PM tasks. Ensure you follow your local
regulations to perform additional PM tasks as necessary.
PM Visit no.
1
2
3
4
5
6
Total time (hours)
6.4
6.7
6.4
6.7
6.4
7.1