Job Card CHK A001 - Boot/Init and Shutdown
Page no. 1733
Chapter 9
JC-CHK-A-001.fm
8-2
Normal power UP sequence check
Start this sequence with the system in the normal switched-off state (above).
1. Press the power ON push-button
I
on the X-ray Console. Power is applied to
all parts of the system:
2. .The Gantry Console central LCD panel displays default settings for kV and
mAs, and displays a message indicating temporary communications errors.
3. The AWS Monitor LED lights. On the UPS the orange LEDs flash during the
selftest process, then the On-line LED
(green) is lit. No red LED should be
lit and no LEDs should continue flashing.
4. The
Login
prompt appears on the AWS monitor within 90 seconds of switch-
on. Log in as described above.
5. The pop-up message
All devices are OK
appears on the AWS monitor.
6. The Gantry Console displays the two following messages:
S70 Wrong appli-
cation selected
and
S34 Select Laterality;
these messages are normal,
because an exam has not been started and no laterality has been selected.
7. The Browser window appears on the AWS monitor
.
Within about 5 minutes of
switching on, it should be possible to use the
Start Exam
button in the
Worklist window (see the
Senographe DS Operator Manual
).
9
POWER ON STATE CHECKS
These checks confirm normal operation after the normal power up sequence (above);
1. The Browser window appears on the AWS monitor.
2. None of the UPS front panel LEDs are flashing; the On–line LED
(green)
is lit.
3. The Conditioner is running (pump audible and no conditioner error messages
displayed).
NOT OK
OK