GE Healthcare
Senographe DS
Revision 1
Service Information and Procedures Class A 2385072-16-8EN
Pre-Installation System Requirements
Page no. 333
Chapter 4
Chap-Pre-Requirements.fm
•
The floor surface must remain horizontal and flat within ±2.5 mm per meter (±
1/10 inch in 39
inches
) after installation of the Gantry.
2. Control Station:
•
The worst case mass of the complete Control Station is 217 kg
(478.4 lbs)
.
•
The bearing surface of the base plate is 0.28 m²
(3 sq. ft.)
.
•
The Control Station is provided with four anchoring points (refer to
•
The floor surface must remain horizontal and flat within ±2.5 mm per meter (±
1/10 inch in 39
inches
) after installation of the Control Station.
The customer is responsible for the structural analysis of the floor and the proposed mounting method.
The customer must hire a structural engineer to design and approve the mounting method, and provide
GEMS with an engineering report. If the results of the structural analysis require stronger anchoring
inserts the defaults supplied in
, the customer must inform GEMS.
Flooring consists of all materials above the structural floor support including subflooring and equipment
support/mounting. The flooring requirements and recommendations are as follows:
•
Flooring materials must support the Senographe system equipment mass, refer to
•
Floors must support the equipment and any transport device used to move the equipment.
•
Flooring throughout the system including X-ray Room must be in accordance with local and national
codes.