Creating an Area Analysis Schedule
Use the following procedure to create a schedule to perform area analysis of masses in a conceptual design,
based on the scenario described in
Area Analysis Example
on page 530. Specific steps may vary depending
on the information that you want to show in the schedule.
To create an area analysis schedule
1
Create mass floors.
See
Creating Mass Floors
on page 525.
2
Click View menu
➤
New
➤
Schedule/Quantities, or on the View tab of the Design Bar, click
Schedule/Quantities.
3
In the New Schedule dialog, do the following:
a
For Category, click Mass Floor.
b
For Name, specify the schedule name.
c
Select Schedule building components.
d
Click OK.
4
On the Fields tab of the Schedule Properties dialog, do the following:
a
For Scheduled fields (in order), add the following fields:
■
Usage
■
Level
■
Mass: Type
■
Floor Area
b
Click Calculated Value.
c
In the Calculated Value dialog, for Name, enter
Floor Area %
.
d
Select Percentage.
e
For Of, select Floor Area.
f
For By, select Grand total.
g
Click OK twice.
5
In the schedule, assign a usage to each mass floor.
Enter text in the Usage column for each level. After entering initial values, for the remaining
rows you can click in the field to select values from a list.
Examples of Conceptual Design Analysis | 531
Summary of Contents for 24000-000000-9860 - Revit Architecture - PC
Page 1: ...Revit Architecture 2009 User s Guide April 2008 240A1 050000 PM02A ...
Page 4: ......
Page 56: ...18 ...
Page 116: ...78 Chapter 3 Revit Essentials ...
Page 172: ...134 Chapter 4 ProjectViews ...
Page 178: ...Schedule with Grid Lines Schedule with Grid Lines and an Outline 140 Chapter 4 ProjectViews ...
Page 554: ...516 ...
Page 739: ...Curtain wall Curtain Grid Curtain Walls Curtain Grids and Mullions 701 ...
Page 1004: ...966 ...
Page 1136: ...1098 ...
Page 1226: ...1188 ...
Page 1250: ...1212 ...
Page 1276: ...1238 Chapter 20 Design Options ...
Page 1310: ...1272 ...
Page 1366: ...1328 ...
Page 1406: ...1368 ...