4
01.99
4.1
General commissioning information
4-116
Siemens AG 2005 All Rights Reserved
SIMODRIVE 611 universal Description of Functions (FBU) – 04.05 Edition
4.1
General commissioning information
The following differentiation is made when commissioning the
”SIMODRIVE 611 universal” control board:
First commissioning
If there is still not a matching parameter set for the drive, then the
drive must be commissioned for the first time.
The drive can be commissioned for the first time using
– the SimoCom U tool
(refer to Chapter 4.3.1)
– the display and operator unit
(refer to Chapter 3.2.1)
Series commissioning
An existing data set can be transferred to the control board via the
SimoCom U tool (refer to Chapter 4.3.2).
Examples:
– Several systems having the same configuration and functions
are to be commissioned.
For the first system, a first commissioning must be executed,
and for additional systems, a series commissioning.
– Replacing a control board.
Note
SimoCom U is a start–up tool for ”qualified commissioning
personnel”
SimoCom U has neither been designed nor is suitable for
operational control of the system!
When called via several PCs, only that PC displays modified data,
from which the changes were also made!
Note
The original status of the board when shipped can always be
re–established as follows:
via P0649 = 1 (from SW 3.1)
via the SimoCom U tool using the ”boot board” function (from
version 03.03)
Commissioning
4 Commissioning
08.01