General commissioning information
4-117
Siemens AG 2005 All Rights Reserved
SIMODRIVE 611 universal Description of Functions (FBU) – 04.05 Edition
The SIMODRIVE 611 universal control board can be commissioned the
fastest if the following prerequisites are checked and fulfilled before
commissioning is started:
Table 4-1
Prerequisites for commissioning
The following conditions must be fulfilled before commissioning!
OK
The SIMODRIVE drive group has been configured.
The wiring has been completed.
The Order Nos. (MLFBs) of the power module, motor and encoder are
known.
Checks for the supply infeed module (NE module)
Switch S1:
Check the settings of this switch at the NE and monitoring module
(e.g.: Has the line supply voltage been set to 400 V or 480 V?)
Reference:
/PJU/, SIMODRIVE 611
Configuration Manual, Drive Converters
The system has been prepared so that it can be powered–up.
The following checklist should help you to simply commission the com-
ponents that we supplied, and to also guarantee a high availability
when used in conjunction with your product:
Observe all of the ESD measures when handling components.
All screws are tightened to the correct torque. Pay special attention
to the DC link bolt connections (1.8 Nm torque).
All connectors are correctly attached and locked/screwed in place.
Screw the control components into the power module.
Observe the power–on sequence in the Configuration Manual.
If the equipment is powered up and down too frequently, the DC link
pre–charging circuit will be inhibited. This can only be re–charged
again after a cooling time of several minutes (e.g. 4 minutes) with
the line supply disconnected (powered down).
Are there line supply/motor contactors connected to the drive con-
verter? It is only permissible to switch these when they are in a no–
current condition.
All components are grounded and correctly shielded.
Connection X131 is grounded.
The load capability of the central power supply system is not ex-
ceeded
Only discharge the unit at the DC link buses through a minimum of
20
Ω
.
Prerequisites
for
commissioning
Check list
for
commissioning
4 Commissioning