Maintenance Commands
555-233-119
576
Issue 5 October 2002
test pms-link
Use test pms-link to run property management system link tests on a pms link. It
checks if the link is accessible, and the long test resets the link. For general
information on PMS links, see
‘‘busyout pms-link’’
. For information on what a PMS
is and does, see
‘‘status pms-link’’
.
Action/
Object
Qualifier
Qualifier Description
Logins
Defaults
Feature
Interactions
test
pms-link
short
long
repeat
number
clear
schedule
Option for a brief series of nondestructive
diagnostic tests.
Option for a longer, more comprehensive
series of both destructive and
nondestructive diagnostic tests.
How many times each test in the
sequence is repeated (1-100)
This option causes the test sequence
(short or long) to repeat until the alarm (if
any) is cleared or a single test in the
sequence fails.
1
Use the screen to schedule execution of
the command. The command is placed in
the command queue and is executed at
the specified time. The information
displayed by the command is sent to the
system printer instead of the screen.
2
Examples:
test pms-link sh r 5
test pms-link l
test pms-link
test pms-link c
test pms-link c sch
1
If no alarms are registered against the maintenance object then the test sequence is run only once. The long
clear option forces a clear of all alarms if no errors are encountered during testing. The short clear option only
clears alarms pertinent to tests in the short sequence.
2
See the Report Scheduler and System Printer feature specification for more details.
init
inads
craft
Test
Sequence
= short;
Repeat = 1
See below
test packet-interface 1a1
TEST RESULTS
Port Maintenance Name Alt. Name Test No. Result Error Code
01A PKT_INT 887 PASS
01A PKT_INT 888 PASS