DIOD-DS1 (DS1 DIOD Trunk)
Issue 5 October 2002
1053
555-233-119
Port Audit and Update Test (#36)
This test sends port level translation data from switch processor to the DS1
Interface circuit pack to assure that the trunk’s translation is correct. Translation
updates include the following data: trunk type (in/out), dial type, timing
parameters, and signaling bits enabled. The port audit operation verifies the
consistency of the current state of trunk kept in the DS1 Interface circuit pack and
in the switch software.
Table 212.
TEST #36 Port Audit and Update Test
Error
Code
Test
Result
Description/ Recommendation
ABORT
Internal system error
1. Retry the command at 1-minute intervals a maximum of 5 times.
2000
ABORT
Response to the test request was not received within the allowable time
period.
2100
ABORT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
FAIL
Test failed due to internal system error.
1. Retry the command at 1-minute intervals a maximum of 5 times.
PASS
Trunk translation has been updated successfully. The current trunk states
kept in the DS1 Interface circuit pack and switch software are consistent. If
the trunk is busied out, the test will not run but will return PASS. To verify
that the trunk is in-service:
1. Enter the status trunk command to verify that the trunk is in-service. If
the trunk is in-service, no further action is necessary. If the trunk is
out-of-service, continue to step 2.
2. Enter the release trunk command to put the trunk back into in-service.
3. Retry the test command.