status hardware-group
Issue 5 October 2002
479
555-233-119
Field descriptions
Hardware Group Command
State:
“active” = testing in progress, “canceled” = testing canceled,
“complete” = command completed; no testing occurring.
Number of MOs Tested:
Number of MOs in the specified group (refer to test
hardware-group command) that the hardware-group
command tests, including MOs that were tested or aborted
due to resource contention.
Total Number of MOs to be
Tested:
Number of MOs in the group specified in the test
hardware-group command.
Percent Complete:
Ratio of the completed MOs to the MOs to test in the
command.
Elapsed Test Time:
Tracks completion time for the
hardware-group command. If
a test cancels and then restarts, the time for the cancel period
is excluded. (HH:MM:SS)
Repetition Number
Number of completed iterations that correspond to the “repeat”
or “continuously” option.
Percentage of Tests
Passed:
Percentage of tests that passed.
Percentage of Tests
Failed:
Percentage of tests that failed.
Percentage of Tests
Aborted:
Percentage of aborted tests
Command:
Hardware-group action objects and qualifiers.
Test sequence:
Short or long.
Test repetition:
Displays continuously or the keyword repeats with the entered
repeat value.
Output options:
Selections that were chosen on the input form: auto-page,
background, or failures.
Hardware options:
Selections that were chosen on the input form: all-ports, or
SPE-interchange.