Testing and Troubleshooting the Octel 50 System
Octel 50 Installation Test Plan
O
CTEL
50 I
NSTALLATION
G
UIDE
13-10
Call Queuing
This section tests the call queuing feature to verify the
appropriate prompts are voiced to callers waiting on hold in
a call queue.
Test:
Make an extension busy.
From an external line, call into the Octel 50
system and dial the busy extension.
Listen to the prompts voiced for the first call
position.
Do not hang up.
Using a second line, call into the system and
dial the busy mailbox.
Listen to the prompts voiced for the second call
position.
Expected Outcome:
Verify the prompts specified under Call Queuing in
System Setup are voiced for the first and second call
queue positions, as appropriate.
Verify custom call queuing prompts are voiced, if they
are recorded.
If this test fails, see the “Call queuing does not work”
section of the Octel 50 Troubleshooting Table for
possible resolutions.
Call Screening
This section tests the call screening feature to verify
subscribers can accept, reject, and reroute callers.
Call Screening Accept
Test:
In a test mailbox, activate the call screening
feature. Call the Octel 50 system and dial the
mailbox number.
Answer the mailbox’s extension when it rings
and press <#> at the call screening prompt to
accept the call.
Expected Outcome:
Verify the system voices to the caller,
“Please speak
your name at the tone so I may say who is calling.”
Verify the caller is transferred and connected to the
extension.
If this test fails, see the “Call screening does not work”
section of the Octel 50 Troubleshooting Table for
possible resolutions.
Содержание Octel 50
Страница 2: ......
Страница 3: ...Octel 50 Installation Guide 585 313 134 Comcode 108503004 101 1840 000 Issue 1 June 1999 ...
Страница 8: ......
Страница 22: ...Determining System Needs Step 3 Consider Additional Hardware Needs OCTEL 50 INSTALLATION GUIDE 2 6 Notes ...
Страница 36: ...Installing the Hardware Step 10 Installing the Sentinel Octel 50 Installation Guide 3 14 Notes ...
Страница 52: ...Running the SMDI Utility Running SMDI as a Standalone Utility Octel 50 Installation Guide 5 4 Notes ...
Страница 180: ...Integrating with an Uninterruptible Power Supply Running UPS Integration Octel 50 Installation Guide 10 4 Notes ...