16-4
Chapter 16
ProDriveNext / EzSQ
16.3.2
EzSQ use procedure
■
Flow up until execution of EzSQ
*1)
By saving the program to the memory element
incorporated in the inverter (data flash), you will also be
able to execute the program after the power supply is
re-turned ON.
If the downloaded program hasn’t been
saved to the memory element, the program will be
erased when the inverter power supply is shut off.
When you create a program and carry out debugs
including operation check, it is recommended to save
after the debugs are completed instead of saving to the
memory element.
*2)
Once the program is downloaded to the inverter, the
EzSQ program becomes executable with the inverter
disconnected from the PC.
• Because SJ-P1 doesn’t share the same parameter
numbers, setting range, the minimum unit, etc. with
conventional models like SJ700/L700, the EzSQ
programs created for these conventional models may not
be used as is. Make sure to carry out re-examination of
the programs and operation checks.
• When a reset or trip reset using the RS terminal is
performed during execution of an EzSQ program, the
program counter will be reset and the program will be
executed from the lead.
No.
Description
Remarks
1
Create an EzSQ program with “ProDriveNext”.
“ProDriveNext” is required.
2
Compile the program in the form executable in the inverter.
As soon as the compiling begins, the grammar of EzSQ program is checked. If
there is an error, the compiling is suspended and the error message appears.
3
Download the compiled EzSQ program to the inverter and save it to the
memory element of inverter.* 1)
4
Set necessary parameters for the inverter.
See "16.3.3 EzSQ function related
parameters".
5
Set the EzSQ function selection [UE-02] to Enable (01 or 02).
6
When UE-02 is set to 01, the PRG terminal is turned ON and the program will
be executed.
When UE-02 is set to 02, the program will be executed automatically after the
power supply is turned ON. 2)
7
The operation state of EzSQ can be checked on the inverter operator keypad.
!
!
Summary of Contents for SJ Series
Page 39: ...5 4 Chapter 5 Included Items Memo ...
Page 55: ...6 16 Chapter 6 Installation Memo ...
Page 91: ...7 36 Chapter 7 Wire Connection and Optional Devices Memo ...
Page 135: ...9 40 Chapter 9 Operating Instructions Memo ...
Page 145: ...10 10 Chapter 10 Test Run Memo ...
Page 159: ...12 2 6 Chapter 12 Inverter Functions Memo ...
Page 169: ...12 3 10 Chapter 12 Inverter Functions Memo ...
Page 195: ...12 5 8 Chapter 12 Inverter Functions Memo ...
Page 217: ...12 8 12 Chapter 12 Inverter Function Memo ...
Page 287: ...12 10 32 Chapter 12 Inverter Functions Memo ...
Page 303: ...12 11 16 Chapter 12 Inverter Functions Memo ...
Page 349: ...12 15 8 Chapter 12 Inverter Function Memo ...
Page 395: ...12 17 34 Chapter 12 Inverter Functions Memo ...
Page 397: ...12 18 2 Chapter 12 Inverter Functions Memo ...
Page 415: ...12 19 18 Chapter 12 Inverter Function Memo ...
Page 581: ...15 10 Chapter 15 Optional Cassettes Memo ...
Page 591: ...16 10 Chapter 16 ProDriveNext EzSQ Memo ...
Page 642: ...18 49 Chapter 18 Tips FAQ Troubleshooting Memo ...
Page 650: ...19 8 Chapter 19 Maintenance and Inspection Memo ...
Page 781: ...Appendix 1 70 Appendix 1 List of Parameters Memo ...