8.1 Outline of OPR control
8.1.1 Two types of OPR control
In "OPR control" a position is established as the starting point (or "OP") when carrying out
positioning control, and positioning is carried out toward that starting point.
It is used to return a machine system at any position other than the OP to the OP when the
QD75 issues a "OPR request" with the power turned ON or others, or after a positioning
stop.
In the QD75, the two types of controls shown below are defined as "OPR control", following
the flow of the OPR work.
These two types of OPR control can be executed by setting the "OPR parameters", setting
"Positioning start No. 9001" and "Positioning start No. 9002" prepared beforehand in the
QD75 to "
Cd.3
Positioning start No.", and turning ON the positioning start signal.
The ZP.PSTRT start numbers of the dedicated instruction can also be set to 9001 or 9002
to execute the OPR control. (For details, refer to CHAPTER 14 "DEDICATED
INSTRUCTIONS".)
(1) Establish a positioning control OP
– "Machine OPR" (positioning start No. 9001)
(2) Carry out positioning toward the OP
– "Fast OPR" (positioning start No. 9002).
The "machine OPR" in (1) above must always be carried out before executing the "fast
OPR" in (2).
REMARK
OPR request
The "OPR request flag" (
Md.31
Status: b3) must be turned ON in the QD75, and a
machine OPR must be executed in the following cases.
•
When the power is turned ON
•
At the ON OFF of the drive unit READY signal (
Md.30
External input/output signal:
b2).
•
At the OFF ON of the PLC READY signal [Y0]
The address information stored in the QD75 cannot be guaranteed while the "OPR
request flag" is ON.
The "OPR request flag" turns OFF and the "OPR complete flag" (
Md.31
Status: b4)
turns ON if the machine OPR is executed and is completed normally.
Summary of Contents for Melsec-Q QD75D1
Page 1: ......
Page 2: ......
Page 22: ...A 20 MEMO ...
Page 24: ...MEMO ...
Page 41: ...1 17 MELSEC Q 1 PRODUCT OUTLINE MEMO ...
Page 48: ...1 24 MELSEC Q 1 PRODUCT OUTLINE MEMO ...
Page 60: ...2 12 MELSEC Q 2 SYSTEM CONFIGURATION MEMO ...
Page 137: ...5 33 MELSEC Q 5 DATA USED FOR POSITIONING CONTROL MEMO ...
Page 232: ...5 128 MELSEC Q 5 DATA USED FOR POSITIONING CONTROL MEMO ...
Page 252: ...6 20 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 253: ...6 21 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL ...
Page 278: ...6 46 MELSEC Q 6 SEQUENCE PROGRAM USED FOR POSITIONING CONTROL MEMO ...
Page 292: ...MEMO ...
Page 436: ...9 120 MELSEC Q 9 MAJOR POSITIONING CONTROL MEMO ...
Page 464: ...10 28 MELSEC Q 10 HIGH LEVEL POSITIONING CONTROL MEMO ...
Page 638: ...14 24 MELSEC Q 14 DEDICATED INSTRUCTIONS MEMO ...
Page 647: ...15 9 MELSEC Q 15 TROUBLESHOOTING MEMO ...
Page 686: ...15 48 MELSEC Q 15 TROUBLESHOOTING MEMO ...
Page 839: ...Appendix 153 MELSEC Q APPENDICES 6 QD75D4N 90 23 27 4 12 98 4 46 Unit mm ...
Page 840: ...Appendix 154 MELSEC Q APPENDICES 7 QD75P1 QD75P2 QD75P4 27 4 23 98 90 4 46 unit mm ...
Page 841: ...Appendix 155 MELSEC Q APPENDICES 8 QD75D1 QD75D2 QD75D4 27 4 23 90 12 98 4 46 unit mm ...
Page 842: ...Appendix 156 MELSEC Q APPENDICES MEMO ...
Page 857: ......
Page 858: ......