9-2
Issue 1.0
March 2001
365-575-389
Installation Manual
Local Installation Testing
Background
Overview
This section describes the LED test, ODU and OMU Verification tests, and
Installation Auto Turnup tests for the WaveStar
TM
OLS 40G at end terminal, dual
facing terminal, and repeater offices. Tests described in this section must be
performed on each shelf.
It also describes testing of:
n
The Optical Translator (OT)
n
The OTU slots
n
The miscellaneous discretes on each OTU and associated wiring to the
EMDU (for Release 2.1 and earlier)
n
The WaveStar OLS 40G/OT integration
n
The optical output of each OTU/OTPM
n
Tests described in the OT subsection must be performed on each OTU/
OTPM and OT cabinet.
General
Considerations
!
CAUTION:
Installation Auto Turnup tests are performed only out of service. If these
tests are performed in service, service will be interrupted.
!
WARNING:
Unterminated optical connectors may emit laser radiation. Do not view
beam with optical instruments. Avoid direct exposure to beam.
Note the following before starting installation Auto Turnup tests:
n
Disconnect the office alarm cable from the WaveStar OLS 40G shelf and/or
OT before performing any tests. Reconnect the office alarm cable after
completing testing.
n
This procedure requires that the NE has WaveStar OLS 40G software
installed. All circuit packs must be installed, with their FAULT LEDs off,
except the OAs which have flashing LEDs. Software Installation and Circuit
Pack Insertion procedures are in Section 9.d
n
No circuit pack should be pulled or inserted while any of the Auto Turnup
tests are in progress.
Содержание WaveStar OLS 40G
Страница 4: ......
Страница 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Страница 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Страница 54: ...1 22 Issue 1 0 March 2001 365 575 389 Installation Manual Overall Installation and Test Considerations...
Страница 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Страница 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Страница 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Страница 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Страница 390: ...8 24 Issue 1 0 March 2001 365 575 389 Installation Manual Network Element Startup and Provisioning...
Страница 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Страница 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Страница 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Страница 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Страница 557: ...Issue 1 0 March 2001 F 1 F PC Setup Usage For CenterLink ManagementConsole F Contents Overview 2...
Страница 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...