7-8
Issue 1.0
March 2001
365-575-389
Installation Manual
Powering
Powering & Testing Procedures
(Continued)
OT Check Battery
Return Cable
Connection
Follow the procedures listed below to check the Battery Return Cable Connection
for OT only installations:
NOTE:
Since the power cable is tied together for all three shelves in a 3-shelf OT
bay, the battery return measurement needs only be taken at one of the
three shelves.
NOTE:
For OLS ONLY Installations, go to the Procedures: page 7-10 section.
(Continued on next page)
Step
Action
Reference
1
Locate the Supply A Power Filter at the left side of the
interconnection panel on Complementary Shelf 2 (Top
Shelf of three-shelf OT bay) or Complementary Shelf 1
(Top Shelf of an Integrated Bay).
2
Remove the spade lug terminal from the top terminal of
the filter. The wire color is black and the terminal is
labeled -48VR. Using an Analog Ohmmeter, measure
the resistance from the wire end to the unpainted cabinet
frame ground.
NOTE:
Digital Multimeter may cause erroneous readings.
Requirement: The resistance shall measure less than
one(1) ohm.
3
After completing the measurement, restore connection
to power filter.
4
At the top right side of Complementary Shelf 2, remove
the screw that holds the fuse panel cover in place and
swing out the fuse panel door.
5
Locate the Supply B Power Filter at the right side of the
interconnection panel.
Содержание WaveStar OLS 40G
Страница 4: ......
Страница 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Страница 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Страница 54: ...1 22 Issue 1 0 March 2001 365 575 389 Installation Manual Overall Installation and Test Considerations...
Страница 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Страница 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Страница 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Страница 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Страница 390: ...8 24 Issue 1 0 March 2001 365 575 389 Installation Manual Network Element Startup and Provisioning...
Страница 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Страница 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Страница 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Страница 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Страница 557: ...Issue 1 0 March 2001 F 1 F PC Setup Usage For CenterLink ManagementConsole F Contents Overview 2...
Страница 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...