F01952
CU DRIVE-CLiQ: Synchronization of component not supported
Message value:
%1
Message class:
Internal (DRIVE-CLiQ) communication error (12)
Drive object:
All objects
Component:
None
Propagation:
DRIVE
Reaction:
OFF2 (NONE)
Acknowledge:
IMMEDIATELY (POWER ON)
Cause:
The existing system configuration requires that the connected DRIVE-CLiQ components support the synchronization
between the basic clock cycle, DRIVE-CLiQ clock cycle and the application clock cycle.
However, not all DRIVE-CLiQ components have this functionality.
Fault value (r0949, interpret decimal):
Component number of the first faulty DRIVE-CLiQ component.
Remedy:
Upgrade the firmware of the component specified in the fault value.
Note:
If required, also upgrade additional components in the DRIVE-CLiQ line.
A01953
CU SYNC: Synchronization not completed
Message value:
%1
Message class:
Internal (DRIVE-CLiQ) communication error (12)
Drive object:
All objects
Component:
None
Propagation:
LOCAL
Reaction:
NONE
Acknowledge:
NONE
Cause:
After the drive system is switched on, the synchronization between the basic clock cycle, DRIVE-CLiQ clock cycle
and application clock cycle was started but was not completed within the selected time tolerance.
Alarm value (r2124, interpret decimal):
Only for internal Siemens troubleshooting.
Remedy:
Carry out a POWER ON (switch-off/switch-on) for all components.
If the error occurs after the drive sampling times were changed, and if a Terminal Module 31 (TM31) is being used,
the sampling times (p0115, p4099) should be set as integer multiples to the drive clock cycles (p0115).
F01954
CU DRIVE-CLiQ: Synchronization unsuccessful
Message value:
%1
Message class:
Internal (DRIVE-CLiQ) communication error (12)
Drive object:
All objects
Component:
None
Propagation:
LOCAL
Reaction:
OFF2
Acknowledge:
IMMEDIATELY (POWER ON)
Cause:
Synchronization between the basic clock cycle, DRIVE-CLiQ clock cycle and application clock cycle was started and
was not able to be successfully completed (e.g. after switch-on).
Fault value (r0949, interpret decimal):
Only for internal Siemens troubleshooting.
Remedy:
1. Remove the cause of a possible DRIVE-CLiQ fault.
2. Initiate a new synchronization, e.g. as follows:
- remove the PROFIBUS master and re-insert again.
- restart the PROFIBUS master.
- switch off the Control Unit and switch on again.
- carry out a Control Unit hardware reset (RESET button, p0972).
- carry out a parameter reset and download the saved parameters (p0009 = 30, p0976 = 2, 3).
Summary of Contents for SINAMICS G130
Page 1: ...s SINAMICS SINAMICS G130 G150 List Manual 07 2016 Edition ...
Page 2: ......
Page 8: ...Preface SINAMICS G130 G150 8 List Manual LH2 07 2016 A5E03263479A ...
Page 1960: ...A Appendix A 3 References SINAMICS G130 G150 1960 List Manual LH2 07 2016 A5E03263479A ...
Page 1974: ...Index SINAMICS G130 G150 1974 List Manual LH2 07 2016 A5E03263479A ...
Page 1975: ......