10-34
Issue 1.0
March 2001
365-575-389
Installation Manual
Fiber Connections
Ring Closure Verification
Background
Line verification procedures check optical line continuity between WaveStar OLS
40G sites. This procedure assumes that the fiber has been connected at each
WaveStar OLS 40G site as detailed earlier in this chapter.
Line Verification
Procedure
Perform the steps in the following table to verify the fiber is properly connected
and the WaveStar OLS 40G sites are communicating with each other:
NOTE:
If at any step the requirements are not met, resolve the problem using
procedures in the 365-575-387 WaveStar OLS 40G User/Service Manual
before proceeding.
Step
Action
1
Log into any WaveStar OLS 40G site using the CMC PC.
2 Execute
CONFIGURATION.Retreive.Ring.Map.
Requirement: Verify the TIDs are all listed correctly. Verify the
communication status is good for each site.
3 Execute
FAULT.Retreive.Alarms.Network.
Requirement: Verify there are no alarms at the requested level.
4 Execute
FAULT.Retreive.Alarms.All.
Requirement: Verify there are no local alarms.
5 Execute
SECURITY.Retreive.System.
Requirement: Verify the APSD state is ENABLED. If it is not, use the
SECURITY.Enter.System command to ENABLE the APSD.
6
Log into another site using the correct TID.
Requirement: Verify the Alarm and Status Report displayed upon logging
in reports no alarms.
7
Execute SECURITY.Retreive.System at the remote site.
Requirement: Verify the APSD state is ENABLED. If it is not, use the
SECURITY.Enter.System command to ENABLE the APSD.
8
Repeat Steps 6 and 7 for all sites in the optical line system.
Summary of Contents for WaveStar OLS 40G
Page 4: ......
Page 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Page 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Page 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Page 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Page 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Page 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Page 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Page 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Page 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...