Issue 1.0
March 2001
5-63
365-575-389
Installation Manual
Wired Cable Installation
OLS/OT Integration Cables
Installation (Continued)
Rack and Stack
Configurations
(continued)
Cable installation for Bays 1-3 continues:
(Continued on next page)
Step
Action
9
Remove the ED-7G045-20 G2 Termination from J7 on the
interconnection panel of the top shelf, OT Complimentary 1 Shelf in Bay
1.
10
Remove the ED-7G045-20 G6 termination from the J15 connector of the
OLS shelf in Bay 1 and discard.
11
Route the P15 end of the ED-7G028-22 G803 cable through the right
side of the OLS shelf in Bay 1 and attach to the J15 BUS IN connector.
12
Route the P5 end of the same ED-7G028-22 G803 cable through the left
side of the OT System Controller Shelf of Bay 2 and connect to the J5
IAOLAN connector.
13
Remove the termination from the J7 connector of the OT System
Controller Shelf of Bay 2.
14
Route the P7 end of the ED-7G045-20 G6 cable through the left side of
the OT System Controller Shelf of Bay 2 and attach P7 to the J7 CTL
OUT connector.
15
Route the P6 end of the same cable through the left side of the OT
Complimentary 1 shelf in Bay 2 and attach P6 to the J6 CTL IN
connector.
16
Route the P9 end of the ED-7G045-20 G7 cable through the left side of
the OT System Controller Shelf of Bay 2 and attach P9 to the J9 EQPG
IN 1 connector.
17
Route the P8 end of the same cable through the left side of the OT
Complimentary 1 shelf in Bay 2 and attach P8 to the J8 EQPG OUT
connector.
18
Route the P13 end of ED-7G045-20 G9 cable through the left side of the
OT System Controller Shelf of Bay 2 and attach P13 to J13 RESET OUT
1 connector.
19
Route the P16 end of the same cable through the left side of the OT
Complimentary 1 shelf in Bay 2 and attach P16 to the J16 RESET IN
connector.
Summary of Contents for WaveStar OLS 40G
Page 4: ......
Page 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Page 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Page 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Page 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Page 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Page 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Page 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Page 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Page 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...