Issue 1.0
March 2001
9-23
365-575-389
Installation Manual
Local Installation Testing
Local Operational Tests
Description
The local operational tests verify that the office alarms and CIT-DTE connections
are operating properly.
Local Alarm Test
Procedure
NOTE:
The following steps should be performed to test the Local Alarms:).
(Continued on next page)
Step
Action
Reference
1
Notify alarm monitoring personnel that testing is taking
place on the office alarm systems.
2
Connect local alarm cable to P29 (OFFICE ALARMS) on
the interconnection panel.
NOTE:
If installing the office alarm cable on an End
Terminal for 4 Line System, use the P29
connector located on the lower shelf. If the upper
shelf is used, the ACO function will not work
properly.
3
Select FAULT.Test.Alarm, enter “all” in the first box,
enter “2” in the Repeat Value box, and hit Enter. The test
will cycle 2 times through each alarm state. The alarm
states are tested in this order: CR, MJ/Prompt. MN/
Deferred, and All Alarm LEDs off.
Requirement: Verify that the office audible alarms,
visual alarms, and the LEDs on the indicator strip are
reflecting the correct alarm status. The NE ACTY will be
lighted throughout the test.
NOTE:
(The ABN, FE ACTY (INFO-F), and NE ACTY
(INFO-N) are not tested
Summary of Contents for WaveStar OLS 40G
Page 4: ......
Page 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Page 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Page 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Page 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Page 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Page 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Page 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Page 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Page 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...