Installation Manual
Wired Cable Installation
OLS/OT Integration Cables
Installation (Continued)
Rack and Stack
Configurations
(continued)
Cable installation for Bays 3-5 continues:
(Continued on next page)
Step
Action
23
Route the P8 end of the same cable through the right side of the OT
Complimentary 2 shelf in Bay 4 and attach P8 to the J8 EQPG OUT
connector.
24
Route the P14 end of the ED-7G045-20 G10 cable through the right side
of the OT System Controller Shelf of Bay 4 and attach P14 to the J14
RESET OUT 2 connector.
25
Route the P16 end of the same cable through the right side of the OT
Complimentary 2 shelf in Bay 4 and attach P16 to the J16 RESET IN
connector.
26
Route the P7 end of the ED-7G045-20 G11A (or G11, G11B) cable
through the left side of the OT Complimentary 1 Shelf of Bay 5 (top shelf)
and attach P7 to the J7 CTL OUT connector.
27
Route the P6 end of the same cable through the left side of the bottom
OT Complimentary 2 shelf in Bay 3 and attach P6 to the J6 CTL IN
connector.
28
Route the P10 end of the ED-7G045-20 G8A (or G8, G8B) cable through
the right side of the OT System Controller Shelf of Bay 5 (middle shelf)
and attach P10 to the J10 EQPG IN 2 connector.
29
Route the P8 end of the same cable through the right side of the bottom
OT Complimentary 2 shelf in Bay 3 and attach P8 to the J8 EQPG OUT
connector.
30
Route the P14 end of the ED-7G045-20 G10A (or G10, G10B) cable
through the right side of the OT System Controller Shelf of Bay 5 (middle
shelf) and attach P14 to the J14 RESET OUT 2 connector.
31
Route the P16 end of the same cable through the right side of the bottom
OT Complimentary 2 shelf in Bay 3 and attach P16 to the J16 RESET IN
connector.
Summary of Contents for WaveStar OLS 40G
Page 4: ......
Page 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Page 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Page 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Page 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Page 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Page 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Page 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Page 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Page 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...