Issue 1.0
March 2001
6-95
365-575-389
Installation Manual
WaveStar OLS 40G Fiber and Circuit Pack Installation
Optical Translator Fiber Installation
Overview
This section covers OT fiber installation. Included is fiber routing, fiber protection,
and labeling.
Fiber Jumper and
Label Installation
Fiber Routing and Installation
The following guidelines should be followed when installing the fibers in the OT
shelves.
(Continued on next page)
Step
Action
1
Fibers are to enter and exit from the side of the shelf that the OTU is
located. For OTUs located left of center, the fiber should be routed to the
left. For OTUs located right of center, the fiber should be routed to the
right.
2
Run fibers into split polyethylene tubes provided in the OT installation kit.
Using cable ties to fasten them, run the tubes to the side of cabinet/frame
in the space between the shelves and the frame. For cabinet installations,
if exiting at the top of cabinet run tubing through innermost rectangular
hole at top of cabinet. See Figure 6-21. For raised floor applications run
the tube out through the bottom of the cabinet, exiting through large holes
in cabinet frame.
3
While routing fibers, do not remove protective covers at end of connector.
4
Before routing fibers, verify which OTU locations are to be used for the
initial installation. Install fibers only at slot locations that are to be used for
this installation.
5
To determine the approximate length of fiber required from the bottom of
the shelf to the OTU input and OTU output, slide an OTU circuit pack into
a shelf without seating it and use it as gauge to determine fiber length.
After determining the lengths for the input and output, remove OTU circuit
pack.
Summary of Contents for WaveStar OLS 40G
Page 4: ......
Page 12: ...Contents xii Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 24: ...Tables xxiv Issue 1 0 March 2001 365 575 389 Installation Manual...
Page 126: ...3 50 Issue 1 0 March 2001 365 575 389 Installation Manual Equipment Installation...
Page 156: ...4 30 Issue 1 0 March 2001 365 575 389 Installation Manual Power Cable Installation...
Page 228: ...5 72 Issue 1 0 March 2001 365 575 389 Installation Manual Wired Cable Installation...
Page 366: ...7 16 Issue 1 0 March 2001 365 575 389 Installation Manual Powering...
Page 436: ...9 46 Issue 1 0 March 2001 365 575 389 Installation Manual Local Installation Testing...
Page 487: ...Issue 1 0 March 2001 12 15 12 Troubleshooting 12 Contents Background 2 Troubleshooting Table 3...
Page 500: ...12 28 Issue 1 0 March 2001 365 575 389 Installation Manual Troubleshooting...
Page 501: ...Issue 1 0 March 2001 A 1 A Releases 1 0 and2 0LBO Selection Tables A Contents Overview 2...
Page 571: ...Issue 1 0 March 2001 H 1 H Optical Protection Switch OPS H Contents Overview 2...