Build Tasks from Links
To build tasks from a link
1
If the TimeLiner window is not already open, click Tools
➤
TimeLiner.
2
In the TimeLiner window, the Links tab, right-click the link you want to use, and click Rebuild Task Hierarchy
from Link on the shortcut menu.
This will import all of the tasks from the project file into TimeLiner.
3
Click the Tasks tab to view the created tasks. The task table is populated in accordance with predefined
settings for the data source. You can make any necessary overrides in the
NOTE
Although the tasks have now been imported into TimeLiner, you still need to
before
you can run a 4D simulation. The fastest way to attach linked tasks is by applying rules (see “
”
on page 358).
Synchronize Tasks with Project Changes
One of the benefits of linking the model to an external project schedule is that any changes to the schedule can
be easily updated in TimeLiner.
To synchronize tasks
1
Make changes to the project in the scheduling software, and save it.
2
Load your model into Autodesk Navisworks (see
3
Click Tools
➤
TimeLiner, and click the Links tab in the TimeLiner window.
4
Right-click the link to the modified project file, and click one of the following options:
■
Rebuild Task Hierarchy from Link. Choose this to re-import all tasks and associated data from the selected
project file, and rebuild the task hierarchy on the Tasks tab.
■
Synchronize Tasks from Link. Choose this to update all existing tasks in the Tasks tab, with the latest
associated data from the selected project file (for example, Start and End dates).
Alternatively, right-click anywhere in the link view, and click Rebuild Task Hierarchy from All Links.
This enables you to re-import all tasks and associated data from all linked project files, and rebuild the task
hierarchy on the Tasks tab.
4D Simulation
In this section, you will learn how to play 4D simulations, and how to customize the simulation playback and
appearance.
Play Simulations
To play a simulation
1
If the TimeLiner window is not already open, click Tools
➤
TimeLiner.
2
On the Tasks tab select the Active check box for all tasks that you want to include in the simulation.
3
Be sure the active tasks are assigned the correct
364 | Chapter 15 Simulate Construction Scheduling
Summary of Contents for 507B1-90A211-1301 - NavisWorks Manage 2010
Page 1: ...Autodesk Navisworks Manage 2010 User Guide March 2009 ...
Page 12: ...xii Contents ...
Page 14: ...2 Part 1 Welcome to Autodesk Navisworks Manage 2010 ...
Page 64: ...52 Chapter 3 Installation ...
Page 97: ...Get a Whole Project View 85 ...
Page 98: ...86 Part 2 Get a Whole Project View ...
Page 136: ...124 Chapter 5 Work with Files ...
Page 178: ...To toggle ViewCube Click View Head Up Display ViewCube 166 Chapter 6 Explore Your Model ...
Page 262: ...250 Chapter 9 Use Viewpoints and Sectioning Modes ...
Page 270: ...258 Chapter 11 Work Within a Team ...
Page 282: ...270 Chapter 12 Share Data ...
Page 346: ...334 Chapter 14 Create Photorealistic Visualizations ...
Page 460: ...448 Chapter 17 Autodesk Navisworks Reference ...
Page 466: ...454 Glossary ...