4
01.99
4.3
Commissioning via SimoCom U
4-122
Siemens AG 2005 All Rights Reserved
SIMODRIVE 611 universal Description of Functions (FBU) – 04.05 Edition
4.3.2
Series commissioning with SimoCom U
For series commissioning of ”SIMODRIVE 611 universal” with the
”SimoCom U” parameterizing and start–up tool, proceed as follows:
1. Power–up the drive group
2. Start SimoCom U
3. Request online operation for drive A
Operator action:
Click–on the ”Search for online drives” in the ”Start–up” menu, and
select ”Drive A” in the selection box.
Is the ”start–up required” window displayed?
– Yes:
––> Click on the ”Load parameter file into the drive...” button
––> After you have selected the required parameter file for drive
A and have pressed ”open”, the file is downloaded into drive A.
– No:
––> Click on the menu ”File ––> Load into drive ––> Load and
save in the drive”
––> After you have selected the required parameter file for drive
A and have pressed ”open”, the file is downloaded into drive A.
Note
If drive B is to be commissioned, then the points must be executed for
drive B from point 3 onwards.
Procedure for
series
commissioning
4 Commissioning