6-43
TI71M01D06-01EN 3rd Edition: 2012.12.01
6.2 Initial
Operation
Test
Unless specifically noted, you should always conduct an initial operation test without
changing #parameters, hard I/O assignment and logic I/O initial value setting from the time of
shipment from the factory before using the drive and motor for the intended application.
Wiring of controller interface is not indispensably needed.
6.2.1 Initial Operation Test Using the Utility Software
Perform an initial operation test using the utility software without load.
Connection
PC on which the utility software is installed
To the control power supply
Motor unit (DM/DR/DB series)
DrvPlll drive
To the main power supply
Home sensor
(Not required in DB series motors)