Pickup1
PU_ST1
TRST1
tReset1
t1
ANSI10000040-3-en.vsd
ANSI10000040 V3 EN-US
Figure 328: Example for Definite Time Delay stage1 operation
9.1.7.3
Blocking
M15326-20 v7
It is possible to block Two step undervoltage protection UV2PTUV (27) partially or completely, by
binary input signals or by parameter settings, where:
BLOCK:
blocks all outputs
BLKTR1:
blocks all trip outputs of step 1
BLK1:
blocks all pickup and trip outputs related to step 1
BLKTR2:
blocks all trip outputs of step 2
BLK2:
blocks all pickup and trip outputs related to step 2
If the measured voltage level decreases below the setting of
IntBlkStVal1, either the trip output of
step 1, or both the trip and the PICKUP outputs of step 1, are blocked. The characteristic of the
blocking is set by the
IntBlkSel1 parameter. This internal blocking can also be set to Disabled
resulting in no voltage based blocking. Corresponding settings and functionality are valid also for
step 2.
In case of disconnection of the high voltage component the measured voltage will get very low.
The event will PICKUP both the under voltage function and the blocking function, as seen in figure
. The delay of the blocking function must be set less than the time delay of under voltage
function.
1MRK 502 066-UUS B
Section 9
Voltage protection
609
Technical manual
Summary of Contents for Relion 670 series
Page 1: ... RELION 670 SERIES Generator protection REG670 Version 2 1 ANSI Technical manual ...
Page 2: ......
Page 48: ...42 ...
Page 62: ...56 ...
Page 182: ...176 ...
Page 692: ...686 ...
Page 726: ...720 ...
Page 1014: ...1008 ...
Page 1242: ...1236 ...
Page 1362: ...1356 ...
Page 1386: ...1380 ...
Page 1422: ...1416 ...
Page 1431: ...1425 ...