Physical and power installation exit checklist
.................................................................................................................................................................................................................................
Verify that all procedures described below have been completed. If a procedure was
not applicable, indicate “N/A”.
Procedure
Result
(Passed/Completed, or
N/A)
Initials
Notes
Rack installed
Rack extension (width) installed
Rack extension (height) installed
Rack adapter kit installed
MDIO terminal rail installed
Subrack installed
Power cables installed
Ground cable installed
Subrack alarm cables installed
Station alarm cable installed
STM-1e cables installed
DS3 cables installed
MDI/MDO cables installed
User byte cables installed
Station clock cables installed
LAN cables installed
Fiber cables installed
Side cover plate installed
Rack door installed
Powering
Fan unit test performed
WaveStar
®
CIT installed
NE software installed
Circuit packs installed
Exit checklist – Part I
.................................................................................................................................................................................................................................
6-2
Lucent Technologies - Proprietary
See notice on first page
365-374-187
Issue 1, December 2005