16.2 Checking Spindle motors and Invertors
16-7
Motor coupling
status
Repetitive runout
-
-
Readjustment by direct-cou-
pled centering
1. Shaft
coupling
2. V-belt
Sunk key
Viewing
Scratch or deformation shall
not exist.
Replacement
Shaft coupling without
key
Dowel marker shall not be
fit loose.
Restoration
Fastening reamer bolt
Shall not become loose.
Retightening
Wear
Wear shall be a little.
Replacement
Motor
Bearing
Hearing, vibration
meter and others
(Check timing: Once
per 12000 hours or 2
years.)
Shall be free from abnormal
sound, increase in noise
level, or temperature rise.
Consumable parts replace-
ment by disassembling and
necessary care
Cooling fan
Hearing, vibration
meter and others
(Check timing: Once
per 15000 hours or 2
years.)
Cooling fan replacement
Oil seal
Viewing (Check tim-
ing: Once per 5000
hours)
Wear shall be a little.
Seal is to be replaced by
being removed from a
machine. Contact our ser-
vice group.
Overall check
Contact our service
group. (Check timing:
Once per 20,000 hours
or 5 years)
-
Do not disassemble and
clean the machine.
Table 16.5 Periodical check
Check object
Check procedure
Criteria
Corrective action
Item
Method
Note that if you are leaving a machine unused for a long time,
take care the following points:
• If you have installed an auxiliary Inverter that is not used normally, check if it operates correctly
by energizing it every 6 month.
Specifically, if you have not used the electrolytic capacitor for more than 1 year, re-transform it
in the following method.
• Open the emergency stop signal and turn on the power. ("CHARGE" indicator turns off.)
• Close the emergency stop signal. ("CHARGE" indicator turns on.)
• In this state, keep energizing it for 30 minutes.
• Slightly rotate the motor axis once a week so that it may be lubricated well.
Summary of Contents for CNC Series
Page 1: ...Maintenance Manual Serviceman Handbook MANUAL No NCSIE SP02 19 Yaskawa Siemens CNC Series...
Page 26: ...Part 1 Hardware...
Page 38: ...System Configuration 1 2 3 Spindle motor designations 1 12...
Page 58: ...Installing the control panels 2 3 5 Installing lightning surge absorbers 2 20...
Page 62: ...Installing the motors 3 4...
Page 84: ...Connection method 4 3 2 Setting the rotary switches on the inverters and servo units 4 22...
Page 96: ...Part 2 Software...
Page 102: ...Software configuration 6 6...
Page 113: ...7 2 Network settings 7 11 8 Click on the radio button to the left of Specify an IP address...
Page 121: ...7 2 Network settings 7 19...
Page 122: ...Part 3 PLC...
Page 154: ...Part 4 Setting up and maintenance...
Page 160: ...Overview of System 10 1 2 Basic operation 10 6...
Page 204: ...How to use Digital Operation 12 2 9 Setting the password setting for write prohibit 12 32...
Page 327: ...Error and Troubleshooting 15 4...
Page 328: ...15 1 Errors without Alarm Display and Troubleshooting 15 5...
Page 329: ...Error and Troubleshooting 15 6...
Page 343: ...Maintenance and Check 16 3 3 Setting up Initializing Absolute encoder 16 14...