Model 4200A-SCS Parameter Analyzer Reference Manual
Appendix K: Using a Signatone CM500 Prober
4200A-901-01 Rev. C / February 2017
K-15
9. Select the
prober-contact
action.
10. Set
chuckposition
to
1
. This moves the Z chuck to the contact position.
11. Place the
prober-separate
action at the bottom of the project tree.
12. Right-click
prober-separate
and select Promote Action twice so that
prober-separate
is at
the site level.
Figure 822: New prober-separate UTM
The position of the action in the project tree determines when the action is run during a test. For
example, in a device with multiple tests, you can run the device level directly. The tests under that
device are executed sequentially. If an action is under the device level, the action runs in sequence
with the tests. Similarly, actions under the subsite, site, or project levels execute automatically when
the subsite, site, or project is run.