750/760 Feeder Management Relay
GE Power Management
17.7 PROTECTION SCHEMES
17 COMMISSIONING
17
c) FOR WYE and DELTA VTs
Test Connections per Figure 17–1: RELAY TEST WIRING – WYE CONNECTION or Figure 17–2: RELAY
TEST WIRING – DELTA CONNECTION on page 17–4.
Indications and Operations are as outlined under Phase Time Overcurrent 1.
Blocking From Logic Inputs:
1.
Inject voltage into the required number of phases to cause a pickup.
2.
Assert a logic input to provide a "Block Undervolt 1 (2)". The PICKUP indicator should immediately go out.
3.
Repeat steps 1 and 2 for logic input “Block 1 TRIP Relay” as required.
Timing:
1.
Connect the “Stop Trigger."
2.
Set the voltage source to nominal voltage.
3.
Reset the timer. Turn the voltage off in the required number of phases, and measure the operating time.
4.
Repeat steps 2 and 3 four more times and obtain an average of the time intervals.
5.
Reset the relay and disconnect the “Stop Trigger.”
17.7.24 LINE UNDERVOLT 3 (4)
Pickup
1.
Inject nominal voltage into the line voltage input of the relay. The PICKUP indicator should be off.
2.
Slowly lower the voltage until the PICKUP indicator comes on. This is the pickup voltage.
3.
Continue to lower the voltage until the PICKUP indicator goes out. This is the programmed Minimum Oper-
ating Voltage minus 2% of VT.
4.
Raise the voltage until the PICKUP indicator comes on, and continue to increase until the indicator goes
out. This is the reset voltage, which should be the pickup value plus 2% of VT.
Indications and Operations are as outlined under Phase Time Overcurrent 1.
Blocking From Logic Inputs:
1.
Inject voltage to cause a pickup.
2.
Assert a logic input to provide a "Block Undervolt 3 (4)". The PICKUP indicator should immediately go out.
3.
Repeat steps 1 and 2 for logic input “Block 1 TRIP Relay” as required.
Timing:
1.
Connect the “Stop Trigger."
2.
Set the voltage source to nominal voltage.
3.
Reset the timer. Turn on the voltage, and measure the operating time.
4.
Repeat steps 2 and 3 four more times and obtain an average of the time intervals.
5.
Reset the relay and disconnect the “Stop Trigger.”
Содержание 750
Страница 2: ......
Страница 4: ......
Страница 124: ...8 14 750 760 Feeder Management Relay GE Power Management 8 12 INSTALLATION 8 S1 RELAY SETUP 8 ...
Страница 144: ...10 14 750 760 Feeder Management Relay GE Power Management 10 10 MISCELLANEOUS FUNCTIONS 10 S3 LOGIC INPUTS 10 ...
Страница 152: ...11 8 750 760 Feeder Management Relay GE Power Management 11 3 OUTPUT RELAYS 3 7 AUXILIARY 11 S4 OUTPUT RELAYS 11 ...
Страница 216: ...12 64 750 760 Feeder Management Relay GE Power Management 12 9 BREAKER FAILURE 12 S5 PROTECTION 12 ...
Страница 484: ...17 78 750 760 Feeder Management Relay GE Power Management 17 10 PLACING THE RELAY IN SERVICE 17 COMMISSIONING 17 ...
Страница 488: ...A 4 750 760 Feeder Management Relay GE Power Management A 1 FIGURES AND TABLES APPENDIXA A ...
Страница 490: ...B 2 750 760 Feeder Management Relay GE Power Management B 1 EU DECLARATION OF CONFORMITY APPENDIXB B ...
Страница 492: ...C 2 750 760 Feeder Management Relay GE Power Management C 1 WARRANTY INFORMATION APPENDIXC C ...
Страница 502: ...x 750 760 Feeder Management Relay GE Power Management INDEX ...
Страница 503: ...GE Power Management 750 760 Feeder Management Relay NOTES ...