17.7 PROTECTION SCHEMES
17 COMMISSIONING
17
17.7.5 PHASE INSTANTANEOUS OVERCURRENT 1
The procedure to test this element is identical to Section 17.7.3: PHASE TIME OVERCURRENT 1 on page
17–21, with the following exceptions. Pickup, Indication and Operation are subject to the test 'phases required
for operation' and not subject to the tests 'linear reset timing' and 'voltage restrained phase time overcurrent'.
Pickup with Two Phases For Operation:
1.
Inject current into phase B at 150% of pickup.
2.
Inject current at a level below the pickup level into phase A.
3.
Slowly increase the phase A current until the PICKUP indicator comes on. Note the pickup value.
4.
Slowly reduce the phase A current until the PICKUP indicator goes out. Note the dropout level, which
should be 2% of CT less than pickup when pickup
≤
CT or 97 to 98% of pickup when pickup > CT.
5.
Repeat steps 1 through 4 for each other pair of phases; B and C, and C and A.
Pickup with Three Phases For Operation:
1.
Inject current into phase B and C at 150% of pickup.
2.
Inject current at a level below the pickup level into phase A.
3.
Slowly increase the phase A current until the PICKUP indicator comes on. Note the pickup value.
4.
Slowly reduce the phase A current until the PICKUP indicator goes out. Note the dropout level, which
should be 2% of CT less than pickup when pickup
≤
CT or 97 to 98% of pickup when pickup > CT.
5.
Repeat steps 1 through 4 for current at 150% in phases C and A and adjusted in B.
6.
Repeat steps 1 through 4 for current at 150% in phases B and A and adjusted in C.
Blocking From Logic Inputs:
1.
Inject current into the required number of phases to cause a pickup.
2.
Assert a logic input to provide a "Block Phase Inst 1". The PICKUP indicator should immediately go out.
3.
Repeat 1 and 2 for logic inputs "Block Phase O/C", "Block All O/C" and “Block 1 TRIP Relay” as required.
Timing:
1.
Connect the Stop Trigger to the interval timer.
2.
Preset the current source to a minimum of 110% of pickup current. Turn the current off, and reset the timer.
3.
Inject the preset current into the required number of phases and note the delay time. Reset the timer.
4.
Repeat step 3 four more times and obtain an average of the time intervals.
5.
Reset the relay and disconnect the “Stop Trigger.”
17.7.6 PHASE INSTANTANEOUS OVERCURRENT 2
The procedure to test this element is identical to that outlined in Section 17.7.5: PHASE INSTANTANEOUS
OVERCURRENT 1 on page 17–24, with the following exception.
Blocking From Logic Inputs:
1.
Inject current into the required number of phases to cause a pickup.
2.
Assert a logic input to provide a "Block Phase Inst 2". The PICKUP indicator should immediately go out.
3.
Repeat 1 and 2 for logic inputs "Block Phase O/C", "Block All O/C" and “Block 1 TRIP Relay” as required.
Содержание 750
Страница 2: ......
Страница 4: ......
Страница 124: ...8 14 750 760 Feeder Management Relay GE Power Management 8 12 INSTALLATION 8 S1 RELAY SETUP 8 ...
Страница 144: ...10 14 750 760 Feeder Management Relay GE Power Management 10 10 MISCELLANEOUS FUNCTIONS 10 S3 LOGIC INPUTS 10 ...
Страница 152: ...11 8 750 760 Feeder Management Relay GE Power Management 11 3 OUTPUT RELAYS 3 7 AUXILIARY 11 S4 OUTPUT RELAYS 11 ...
Страница 216: ...12 64 750 760 Feeder Management Relay GE Power Management 12 9 BREAKER FAILURE 12 S5 PROTECTION 12 ...
Страница 484: ...17 78 750 760 Feeder Management Relay GE Power Management 17 10 PLACING THE RELAY IN SERVICE 17 COMMISSIONING 17 ...
Страница 488: ...A 4 750 760 Feeder Management Relay GE Power Management A 1 FIGURES AND TABLES APPENDIXA A ...
Страница 490: ...B 2 750 760 Feeder Management Relay GE Power Management B 1 EU DECLARATION OF CONFORMITY APPENDIXB B ...
Страница 492: ...C 2 750 760 Feeder Management Relay GE Power Management C 1 WARRANTY INFORMATION APPENDIXC C ...
Страница 502: ...x 750 760 Feeder Management Relay GE Power Management INDEX ...
Страница 503: ...GE Power Management 750 760 Feeder Management Relay NOTES ...