6. Transport
The customer must make the necessary arrangements to move
the machinery from the truck to its final installation site.
The transport route to the machine’s installation site must be
clarified in good time prior to the machine’s delivery. Especially
gates, header heights, cable rack heights, ground conditions for
armored rollers, etc. need to be checked
The conditions for transporting the equipment are contained in the
transport regulations.
•
TLC 1005: Transport regulations, drawing no. 93918-8-10
mat. no. 0920706
•
Cross beam (on loan), carrying capacity 12 t or 15 t.
•
Crane truck, min. carrying capacity 12 t.
•
Chains and transport belts.
•
Four M12 eyebolts.
•
Fork lift truck, min. carrying capacity 2.5 t.
•
Gantry crane, carrying capacity 12 t or armored rollers
(1 steerable, 2 fixed).
•
Hydraulic hoisting jack:
–
TLC 1000: 3 jacks with a carrying capacity of at least 5 t
(attachment height
≤
50 mm).
–
TLC 1005: 4 jacks with a carrying capacity of at least 8 t
(attachment height
≤
50 mm).
•
Hoisting iron (1 m) and extension.
•
2 double ladders, each 4 m high.
•
Lift
truck.
TLC 1005: The basic machine is delivered with a cross beam (on
loan) to facilitate transport. The cross beam and the swivel bearers
that are installed in the machine body must be returned to
TRUMPF after system installation and start-up.
TLC 1005 with raised machine body: It is essential that a crane
is available at the installation site during the installation of
machines with a base or two station operation, in order to set the
machine body on the base.
TLC 1000: The basic machine is delivered fully assembled (with
guide carrier, Z slide, and laser) with a transport frame.
Transport regulations
Auxiliary and transport
equipment
Summary of Contents for LASERCELL 1005
Page 1: ...Operator s manual TRUMPF LASERCELL 1005...
Page 2: ......
Page 3: ...Operator s manual TRUMPF LASERCELL 1005 Edition 07 2004...
Page 6: ...0 6 Before You proceed B337EN00 DOC...
Page 22: ...0 22 Table of Contents B337EN00 DOC...
Page 23: ...1...
Page 61: ...1 38 Laser processing B337EN01 DOC...
Page 62: ...2...
Page 107: ...3...
Page 160: ...4...
Page 408: ...4 248 Operation B337EN4_8 Fig 36634 Fig 36630 4 Select Backup to ZIP press 4 5 Press Enter...
Page 412: ...4 252 Operation B337EN4_8...
Page 413: ...5...
Page 515: ...5 102 Further service programs B337EN05 DOC...
Page 516: ...6...
Page 589: ...7...
Page 628: ...8...
Page 636: ...8 8 Cross hairs to cut out B337EN08 DOC...
Page 637: ...9...
Page 643: ...9 6 Diagram Location of measuring points B337EN09 DOC...
Page 644: ...10...