2-44
Installation conditions TLC 1000 and TLC 1005 - Version 5
B337EN02.DOC
Time before
delivery of the machine
Planning criterion
Action
12 weeks,
but no later than calendar week ...
Gas supply
Arrange for installation of the
laser and cutting gas supply at
the installation site.
Decide on the gas supply
method (cylinders, cylinder
bundles, gas tank).
Note the valves and fittings
required (e.g. two-stage
pressure reducer).
Consult your gas supplier to
make a layout for the gas lines.
12 weeks,
but no later than calendar week ...
Compressed air supply
Install a compressed air supply
at the installation site
(connection, purity, compressed
air requirements).
4 weeks,
but no later than calendar week ...
Working materials
Acquire stocks of operating
materials:
laser gases, cutting gases, and
operating materials for the
cooling unit.
4 weeks,
but no later than calendar week ...
Transport
Make sure that the transportation
aids required are available.
2 weeks
but no later than calendar week ...
Prepare
foundation
Prepare the foundation (bore
holes and cutouts) of the
machine according to the
foundation plan.
At installation and start-up
Ensure electricians are
available
Connect the machine to the
electrical supply.
In the course of installation
by the servicing technician
Transport
A crane must be available for
installing raised machine bodies
and machines with two station
operation.
Table 2–29
Summary of Contents for LASERCELL 1005
Page 1: ...Operator s manual TRUMPF LASERCELL 1005...
Page 2: ......
Page 3: ...Operator s manual TRUMPF LASERCELL 1005 Edition 07 2004...
Page 6: ...0 6 Before You proceed B337EN00 DOC...
Page 22: ...0 22 Table of Contents B337EN00 DOC...
Page 23: ...1...
Page 61: ...1 38 Laser processing B337EN01 DOC...
Page 62: ...2...
Page 107: ...3...
Page 160: ...4...
Page 408: ...4 248 Operation B337EN4_8 Fig 36634 Fig 36630 4 Select Backup to ZIP press 4 5 Press Enter...
Page 412: ...4 252 Operation B337EN4_8...
Page 413: ...5...
Page 515: ...5 102 Further service programs B337EN05 DOC...
Page 516: ...6...
Page 589: ...7...
Page 628: ...8...
Page 636: ...8 8 Cross hairs to cut out B337EN08 DOC...
Page 637: ...9...
Page 643: ...9 6 Diagram Location of measuring points B337EN09 DOC...
Page 644: ...10...